1 billable time
An amount of time in which work or a task is performed. A client/customer can be charged for the time spent performing the task. -
2 critical task
"A task that must be completed on schedule for the project to finish on time. If a critical task is delayed, the project completion date might also be delayed. A series of critical tasks makes up a project's critical path." -
3 split task
"A task that is scheduled for non-contiguous periods of time. For example, a two-day task that does not require contiguous work might be split so that the first day of work is scheduled for Monday, and the second day is scheduled for Thursday." -
4 lag time
"A delay between tasks that have a dependency. For example, if you need a two-day delay between the finish of one task and the start of another, you can establish a finish-to-start dependency and specify a two-day lag time [has a positive value]." -
5 lead time
"An overlap between tasks that have a dependency. For example, if a task can start when its predecessor is half-finished, you can specify a finish-to-start dependency with a lead time of 50 percent for its successor [has a negative lag value]." -
6 report period
"The span of time during which you track and update a task that the workgroup manager has assigned to you. You can change the unit of time to days, weeks, or a single unit of time for the whole task." -
7 assignment delay
The amount of time between the scheduled start of a task and the time that the assigned resource is to start working on the task. -
8 delay
The amount of time between the scheduled start of a task and the time when work should actually begin on the task; it is often used to resolve resource overallocations. There are two types of delay: assignment delay and leveling delay. -
9 expected duration
"The total span of active working time expected for a task, that is, the amount of time from the expected start to the expected finish of a task." -
10 optimistic duration
"The best-case possibility for the total span of active working time expected for a task, that is, the amount of time from the optimistic start to optimistic finish of a task." -
11 pessimistic duration
"The worst-case possibility for the total span of active working time expected for a task, that is, the amount of time from the pessimistic start to pessimistic finish of a task." -
12 set
I[set] n լրակազմ, հավաքակազմ. հավաքածու. (կինո) նկարահանման հրապարակ. թատր. բեմանկար, դեկորացիա. set of stamps նամականիշների հավաքածու. a tea/dinner set ճաշի/թեյի լրակազմ/սպասք. a set of teeth ատամների պրոթեզ. set of principles/procedures սկզբունքների/ընթացակարգերի ամբող ջու թյուն. a complete set of Dickens Դիքենսի ստեղծագործությունների ժողո վածու. (խումբ, մարդկանց շրջան). the smart/literary set պերճաշուք, մոդայա կան/ գրա կան շրջաններ. He doesn’t belong to their set Նա նրանց շրջանին չի պատկանում. (կեցվածք, ուղղվածություն) the set of the head գլուխը պահելու ձևը. make a dead set խիստ հետապնդել մեկին. (շարք) a set of lectures դասախոսությունների մի ամ բողջ շարք. (սարք, ապարատ) receiving set ռադիոընդունիչ. TV set հեռուստացույցII[set] a սառած, քարացած. a set smile սառած ժպիտ. his face set քարացած դեմքով. (պատրաստ) set to begin պատրաստ սկսելու. All set? Բոլորը պատրա՞ստ են. (կայուն, կայունացած) a set time/task որոշակի ժա մանակ/հանձնարարություն. set rules/limits սահմանված կանոններ/սահմաններ. a set lunch կոմպլեքսային ճաշ. set in one’s ways կայունացած սովորույթներ. The weather is set Եղանակը կայունացել է. set books (ուսմ.) պարտադիր գրականություն. (վճռական) dead set against վճռականորեն դեմ լինել. set in one’s purpose վճռական լինել իր մտադրության մեջ[set] v դնել, տեղավորել. set the plates/food on the table ափսեները/ուտելիքը դնել սեղանին. set in order կարգի բերել. set in motion շարժման մեջ դնել. set on foot սկսել, ձեռնարկել. set at liberty/free ազատել. The story is set Գործողությունը տեղի է ունենում. set the watch by radio ժամացույցը ռադիոյով ուղղել. set one’s hair մազերը կարգի բե րել/ հարդարել. set a bone բժշկ. ոսկորը տեղը գցել. (սահմանել, նշանակել) set limits սահմաններ դնել/նշանակել. set a task առա ջադրանք դնել. set a precedent նախադեպ ստեղծել. set an example օրինակ ծառայել. set an exam paper քննատոմսեր կազմել. set a record ռեկորդ սահմանել. set time/date ժամանակ/օր սահմանել. set to work աշխատանք սկսել/աշխա տանքի անց նել. set the pace տեմպ տալ. set once teeth ատամները սեղմել. set eggs ձվերը թուխս դնել set to music երժշտության վերա ծել. (պատճառել, ստի պել) set to work գոր ծի դնել. set smn thinking ստիպել մտածել, մտա ծել տալ. set laughing ծիծաղեցնել. (նստել) The sun/The moon set Արևը/Լուսինը մայր մտավ. (կարծրանալ, պնդանալ) The jelly/The cement has set Դոնդողակը/Ցեմենտը սառել/ կարծ րացել է. set against գրգռել, դեմ տրա մադրել. set fire to, set on fire հրկիզել. set the table սեղանը գցել. set in order կարգի բերել. set eyes (on) տեսնել. set foot ոտք դնել. set aside մի կողմ դնել. առանձնացնել. set aside a verdict իրավ. դա տավճիռը չեղյալ համարել. set back հետ գցել, շարժումը կասեցնել. set back the programme ծրագիրը կասեցնել/հետ գցել. set down ցած դնել/իջեցնել. վայր բերել. set in սկսվել, գալ, վրա հասնել. Winter has set in Ձմեռը եկել է. Reaction set in փխբ. Սկսվեց ռեակցիան. set forward առաջ քաշել, առաջար կել. set on հրահրել, հարձակվել. set out ցու ցադրել, ի ցույց դնել. շարադրել. She set out her best China Նա ցուցադրել էր իր լավա գույն սպասքը. set out rules/conditions կանո ն ներ/պայմաններ շարադրել. (ճանապարհ ընկնել) set out in search of գնալ փնտրել. set straight կարգավորել. set things straight գոր ծերը կարգավորել. set up կանգնեցնել. set up a new government նոր կառավարություն ձևա վորել/կազմել. set up in business իր գործը բա ցել. set upon հար ձակվել, նետվել. հմկրգ. set up disk բեռնման սկավառակ -
13 bot
"A program that performs a task on a network, especially a task that is repetitive or time-consuming." -
14 robot
"A program that performs a task on a network, especially a task that is repetitive or time-consuming." -
15 free slack
The amount of time that a task can slip before it delays another task. -
16 remaining duration
The amount of time left to work on a task before the task is completed. This is calculated as follows: Remaining Duration = Duration - Actual Duration. -
17 slippage
The amount of time that a task has been delayed from its original baseline plan. The slippage is the difference between the scheduled start or finish date for a task and the baseline start or finish date. -
18 processor
[΄prəusesə] n հմկրգ. հրա հանգ կատարող սարք. processor active task ընթացիկ խնդիր, առաջադ րանք. processor bound task հաշվարկային խնդիր, առաջադրանք. processor defined function դեպի մեքենան կողմնորոշված ֆունկցիա. processor interrupt պրոցեսորի ընդ հատում. processor time հաշ վար կի ժամանակ -
19 multithreading
"Running several processes in rapid sequence within a single program, regardless of which logical method of multitasking is being used by the operating system. Because the user's sense of time is much slower than the processing speed of a computer, multitasking appears to be simultaneous, even though only one task at a time can use a computer processing cycle." -
20 Actual Capacity
"The amount of time a resource has available to work at any given point in time. Actual Capacity is equal to Capacity minus resource calendar exceptions (e.g. offsite training, morale events, jury duty) and previously scheduled committed work (Project task assignments with type = committed). This is the most valuable measure for scheduling a resource."
- 1
- 2
См. также в других словарях:
task time — noun : the time set in a incentive wage system as proper for the performance of an industrial operation by a worker … Useful english dictionary
task — [tɑːsk ǁ tæsk] noun [countable] 1. a piece of work that must be done, especially one that must be done regularly: • Scheduling is a key task for most managers. • day to day management tasks • computers that can do dozens of tasks at the same time … Financial and business terms
Time management — is commonly defined as the various means by which people effectively use their time and other closely related resources in order to make the most out of it. [The Concise Dictionary of Business Management, by David A. Statt, Taylor Francis Group… … Wikipedia
Task Scheduler — is a component of Microsoft Windows that provides the ability to schedule the launch of programs or scripts at pre defined times or after specified time intervals. It was first introduced in the Windows 95 Plus! pack as System Agent [cite web url … Wikipedia
Task Force Faith — Task Force Faith, also sometimes referred to as Task Force Maclean (and by its official designation, RCT 31) was a United States Army unit destroyed in fighting at the Battle of Chosin Reservoir during the Korean War between November 27 and… … Wikipedia
Task Force 31 — (TF 31) was a US Navy task force active with the United States Third Fleet during World War II, and still ready to be activated today with today s Third Fleet. Task Force numbers were in constant use, and there were several incarnations of TF 31… … Wikipedia
Task management — is a process of managing task (or task portfolio) during its lifecycle, including planning, testing, tracking and reporting.Effective task management suppose managing all aspects of a task including its status, priority, time, human and financial … Wikipedia
Task Force Tarawa — (TFT) was the name given to the 2nd Marine Expeditionary Brigade during the 2003 invasion of Iraq. They were a Marine Air Ground Task Force commanded by Brigadier General Richard Natonski Natonski message.] that was attached to the I Marine… … Wikipedia
Task loading — in Scuba diving is a term used to refer to a multiplicity of responsibilities leading to an increased risk failure on the part of the diver to undertake some key basic function which would normally be routine for safety underwater. [cite journal… … Wikipedia
Task analysis — is the analysis of how a task is accomplished, including a detailed description of both manual and mental activities, task and element durations, task frequency, task allocation, task complexity, environmental conditions, necessary clothing and… … Wikipedia
Task Force 145 — is a combined U.S. and British military special forces group specifically charged with hunting down al Qaeda leader Osama bin Laden and, prior to his death on June 7, 2006, Al Qaeda in Iraq leader Abu Musab al Zarqawi. It is a continuation of a… … Wikipedia